Date Done Activity Type Activity Comments   (mouse over for more text) ETA Link
 2/22/1994  Waste Tire Processing Facility Inspection.   Not Processing Or Storing Tires At This Time  
 8/10/1994  Compliance Inspection   Quarterly Compliance Inspection  
 12/16/1994  Compliance Inspection   Quarterly Compliance Inspection  
 2/23/1995  Waste Tire Processing Facility Inspection.   Site Is In Compliance With Waste Tire Rule For Wtpf  
 7/28/1995  Compliance Inspection    
 9/14/1995  Waste Tire Processing Facility Inspection.   Site Is Temporarily Closed, Not Recieving Tires  
 1/17/1996  Waste Tire Processing Facility Inspection.   Lurix Inspected. Site Is Closed And Not Receiving Tires Presently. Yearly Cce Is Due Before 16-Feb-96  
 5/30/1996  Non-Compliance Letter Issued    
 6/26/1996  Compliance Inspection   Expired Permit, New Permit Being Processed  
 6/28/1996  Compliance W/O Formal Enforcement Action   New Permit Issued  
 10/28/1996  Compliance Evaluation Inspection    
 12/12/1996  Compliance Evaluation Inspection   Drum Incorrectly Labeled, Water Seepage In Ne Corner  
 3/7/1997  Compliance Evaluation Inspection   Previous Items Corrected | Mw Pad And Secondary Containment Damaged  
 6/4/1997  Renewal Application Due   Renewal Application For Soils Mrf Is Due  
 6/20/1997  Compliance Evaluation Inspection    
 7/2/1997  Permit Condition Or Consent Order/Response Due   Minor Modification Of S013-300512, File Number So13-308094  
 7/30/1997  Document Forwarded For Technical Review   Alt. Procedure Request To Bwc  
 9/26/1997  Compliance Evaluation Inspection   Check Last Insp. | Some Drums Temp. Outside Soil Bldg.  
 11/19/1997  Waste Tire Processing Facility Inspection.   Meeting With Mike Vardamen Of Rinker This Date Revealed That Rinker Has Not And Is Not Accepting Any Waste Tires For Burning At This Time Due To The Economics Of Waste Tire Disposal In Dade County, Memo To File  
 12/4/1997  Compliance Evaluation Inspection   Previous Deficiencies Corrected.  
 3/4/1998  Compliance Evaluation Inspection   Elevated Dl On Some In House Gw Parameters  
 3/5/1998  Waste Tire Processing Facility Inspection.    
 3/11/1998  Letter   Closure Cost Est. Didn'T Include The Costs Of The Trailers, Therefore Deined Until Cce Is Revised | Received Revised Cce And Approved, Sent To Tlh  
 6/10/1998  Compliance Evaluation Inspection   Elevated Dl On Some In House Gw Parameters  
 8/10/1998  Telephone Conversation   Per Vp Of Rinker, Facility Is Not Accepting Any Waste Tires For Burning At Plant  
 9/14/1998  Compliance Evaluation Inspection    
 1/7/1999  Compliance Evaluation Inspection   Sw Well Cap Not Sealing  
 1/11/1999  Renewal Application Due   Renewed Wtpf Permit  
 5/11/1999  Waste Tire Processing Facility Inspection.   S. Beregovoy. As Per Mr. Emery, No Tires Are Currently Being Accepted Or Stored At This Site. Csr Rinker Materials Intend To Retain The Permit As They Plan To Resume Tire Processing In The Future.  
 5/11/1999  Material Recovery/Recycler Inspection.   S. Beregovoy Inspected. A Pile Of Rocks Separated From The Screened Hydrocarbon Contaminated Soil Was Stored On Impermeable Surface Outside The Delineated Soil Storage Area. It Was Not Covered. Mr. Emery Informed Me That All Materials Stored Outside  
 6/3/1999  Compliance Evaluation Inspection/Waste Cleanup   In Compliance, Suggested Permit Review For New Process  
 6/29/1999  Letter   Alt. Procedure For Key West Naval Sta. Pcb Contaminated Soils  
 9/29/1999  Compliance Evaluation Inspection/Waste Cleanup   Oil Inside Secondary Containment Of Bldg.,Need To Remove And Identify Source  
 10/26/1999  Material Recovery/Recycler Inspection.   S. Beregovoy Inspected. The Berms At The Entrance To The Soil Storage Facility Had Been Recently Repaired. All Soil Was Stored Within The Storage Area. There Was A Roll-Off Container With Wood, Plastics And Other Materials Not Intended For Incinerati  
 10/26/1999  Waste Tire Processing Facility Inspection.   S. Beregovoy Inspected. No Waste Tires Are Currently Processed At This Facility. There Are No Plans To Process Waste Tires In The Immediate Future.  
 12/23/1999  Monitoring Data Results Reviewed   Need To Update Mw Map And Get Better Mdl For As And Se | 4q99 Gmr  
 12/29/1999  Compliance Evaluation Inspection/Waste Cleanup   Oil Removed From Previous Insp.,No Problems Noted.  
 1/20/2000  Material Recovery/Recycler Inspection.   S. Beregovoy Inspected. Temporary Repairs To A Damaged Berm At The Soil Storage Facility. No Thermal Soil Treatment For The Past Week Due To Routine Equipment Maintenance.  
 5/12/2000  Waste Tire Processing Facility Inspection.   S. Beregovoy Inspected. Waste Tires Are Currently Not Processed At This Facility.  
 5/12/2000  Material Recovery/Recycler Inspection.   S. Beregovoy Inspected. Recently Repaired Berms At The Entrance To The Soils Storage Building. All Rejected Large Size Aggregate Is Stored In A Roll-Off Container.  
 10/12/2000  Waste Tire Processing Facility Inspection.   S. Beregovoy Inspected. No Tires Are Currently Being Accepted At This Facility.  
 10/12/2000  Material Recovery/Recycler Inspection.   S. Beregovoy. Newly Repaired Berms. All Waste Materials Were Confined To The Roofed Area.  
 1/26/2001  Material Recovery/Recycler Inspection.   S. Beregovoy Inspected. The Facility Receives Up To 10,000 Tons Per Month Of Contaminated Soil. I Advized Mr. Emery To Repair A Portion Of The Berm At The Facility'S Entrance.  
 5/22/2001  Material Recovery/Recycler Inspection.   S. Beregovoy Inspected. All Berms At The Entrance To The Soil Storage Area Had Been Recently Repaired. The Facility Is Currently Operating At Its Capacity Receiving Up To 10,000 Tons Of Contaminated Soil Per Month.  
 5/22/2001  Waste Tire Processing Facility Inspection.   S. Beregovoy Inspected. No Waste Tires Are Currently Accepted Or Processed At This Facility.  
 10/24/2001  Waste Tire Processing Facility Inspection.   Alejandro Vergara Performed The Inspection. The Waste Tire Processing Facility Was Not In Operation At This Time.  
 10/24/2001  Material Recovery/Recycler Inspection.   Alejandro Vergara Performed The Inspection. Contaminated Soils Were Observed Inside Of Building A. The Facility Did Not Appear To Have An Excess Of Material.  
 1/29/2002  Material Recovery/Recycler Inspection.   Routine Inspection Conducted And One Damaged Monitoring Well Noted That Needs Repairing. Amounts On Site Were Within Permit Limits.  
 5/13/2002  Waste Tire Processing Facility Inspection.   Inspection Conducted By K. Yipon. The Waste Tire Operation Is Remains Inactive. The Kiln That Was Used In The Process Is Longer Operative And There Were No Waste Tires On Site.  
 5/13/2002  Material Recovery/Recycler Inspection.   Inspection Conducted By K.Yipon. The Facility Has Applied For A New Permit And It Was Granted. The 4 Wells Are Intact. The Amount Of Soil On Site Was Within Permitted Amount.  
 10/24/2002  Waste Tire Processing Facility Inspection.   K.Yipon Conducted Inspection. No Tires On Site. The Facility Is Not In Operation But Maintains The Permit.  
 10/24/2002  Material Recovery/Recycler Inspection.   K. Yipon Conducted Inspection. The Cover Of The Northwest Corner Monitoring Well Must Be Replaced. Soils Witin Permitted Amounts.  
 1/14/2003  Material Recovery/Recycler Inspection.   Inspection Done By Kyipon. No Violations Observed. The Nw Monitoring Well Was Repaired And The Other 3 Around The Soil Storage Building Were In Tact. | The Incoming Soil Amounts Were Within Permitted Amounts.  
 5/20/2003  Waste Tire Processing Facility Inspection.   Inspection Done By Kyipon. The Facility No Longer Collects Waste Tires For The Kiln. This Kiln Has Since Been Dis-Assembled.  
 5/20/2003  Material Recovery/Recycler Inspection.   Inspection Done By K Yipon. Soil Within Permitted Amounts. No Leachate Observed In Soil Storage Area. Explained That Company May Need To Show That Leachate System Is Not Needed Before Possible Changes Can Be Made To The Permit.  
 10/30/2003  Waste Tire Processing Facility Inspection.   Inspection Done By Kyipon. No Activity Observed On Site. No Tires Are Stored For Processing Since The Kiln That Was Used In The Past Is Not In Operation.  
 10/30/2003  Material Recovery/Recycler Inspection.   Inspection Done By Kyipon. Facility Has Repaired The Leachate Pump. Soil Amounts Were Within Permitted Limits.  
 1/28/2004  Material Recovery/Recycler Inspection.   Inspection Done By Kyipon. Facility Had Less Than The Permitted Amount Of Contaminated Soil And The Leachate System Was Operational.  
 5/27/2004  Material Recovery/Recycler Inspection.   Inspection Done By K Yipon. The Soil Amounts Were Within The Permitted Limit. The Wells Appeared To Be Good Working Condition.  
 5/27/2004  Waste Tire Processing Facility Inspection.   Inspection Done By K Yipon. The Facility Is In The Porcess Of Renewing This Permit. They Have Not Been Receiveing Waste Tires But Have Kept The Permit Active. No Waste Tires Observed On Site.  
 10/18/2004  Material Recovery/Recycler Inspection.   Inspection By Kyipon. There Was Approx. 3800 Cuyds Of Unscreened Contaminated Soils And Approx. 2600 Cuyds Of Screened Contaminated Soils In The Storage Building. | The Screener Was On Site Inside The Building And There Were No Soils Stored Outside O  
 10/18/2004  Waste Tire Processing Facility Inspection.   Inspection Done By Kyipon. The Facility Had An Active Permit But The Operators Have Not Been Collecting Or Storing Any Waste Tires On Site. The Kiln Was Not In Operation And There Were No Waste Tires On Site.  
 1/31/2005  Material Recovery/Recycler Inspection.   Inspection Done By Kyipon. The Soil Was Properly Stored Within The Soil Storage Building. The Unacceptables Material Was Also Stored Within The Building. The Monitoring Wells Were In Tact And The Leachate Collection System Was Cleared And Operational  
 5/31/2005  Waste Tire Processing Facility Inspection.   Inspection Done By Kyipon. The Company Had Renewed The Permit Which Was Issued In October 2004. No Waste Tires Have Been Collected As Of Yet And No Processing Of Tires Is Ongoing At The Site. The Kiln To Burn Tires Is Not In Operation As Of Yet.  
 5/31/2005  Material Recovery/Recycler Inspection.   Inspection Done By Kyipon. The Contaminated Soil Stored On Site Was Within The Permitted Limits. There Was Approx. 2500cuyds Of Unscreened Soil And 1000cuyds Of Concrete. No Violations Observed.  
 10/31/2005  Material Recovery/Recycler Inspection.   Inspection Done By Kyipon. The Contaminated Soils Stored On Site Were Within The Permitted Amounts And The Unacceptables Were Properly Stored. No Damaged Was Sustained At The Soil Storage Building.  
 10/31/2005  Waste Tire Processing Facility Inspection.   Inspection Done By Kyipon. There Were No Waste Tires Stored Or Accepted On Site Since The Processing Equipment Was Not Assembled. The Permit Is Kept Active In The Event That The Operators Decide To Collect Waste Tires For Energy Use.  
 1/5/2006  Groundwater Monitoring Report   Groundwater Monitoring Report Submitted.  
 1/20/2006  Material Recovery/Recycler Inspection.   Inspection Done By Kyipon. The Contaminated Soil Amounts Were Within The Permitted Limits. There Were Approx. 10000cuyds Of Unscreened Soil And 3500cuyds Screened Soil. | The Unacceptables Were Properly Stored And The Wells Were Tested In The Last We  
 5/30/2006  Material Recovery/Recycler Inspection.   Inspection Done By Kyipon. I Observed That There Were Approx. 5000cuyds Of Unscreened And 1000cuyds Of Screened Contaminated Soil In The Storage Building. The Unacceptables Were Stored In | Two Roll-Offs In Front Of The Building. No Violations Observ  
 5/30/2006  Waste Tire Processing Facility Inspection.   Inspection Done By K Yipon. The Operators Have Maintained The Permit But Have Not Initiated Collection And /Or | Processing Of Waste Tires On Site. There Were No Tires Stored On Site During The Inspection.  
 6/13/2006  Financial Assurance Documents   Iafacc Est Approved  
 9/29/2006  Groundwater Monitoring Report   Groundwater Monitoring Report Submitted.  
 10/30/2006  Waste Tire Processing Facility Inspection.   Inspection Done By K Yipon. No Areas Of Concern. The Operators Have Begun Testing The Burner By Introducing Approx. 300tires Per 24hr. Period Once Per Week To Guage The Enger Generated From The Tire Consumption. | The Tires Area Stored In A Trailer  
 10/30/2006  Material Recovery/Recycler Inspection.   Inspection Done By Kyipon. No Areas Of Concern; I Observed That There Were Approx. 550cuyds Of Incoming Unscreened, Unprocessed Soil And Approx. 2500cuyds Screened Soil (Unprocessed) On Site. All Incoming Soil Was Stored Inside Building And Unaccept  
 1/31/2007  Material Recovery/Recycler Inspection.   Inspection Done By K Yipon. No Areas Of Concern. There Were Approx. 9000cuyds Of Incoming Unscreened, Inprocessed Soil And Approx. 2000cuyds Screened Soil (Unprocessed) On Site. All Incoming Soil Was Stored Inside The Building And The Unacceptables  
 6/12/2007  Material Recovery/Recycler Inspection.   Inspection Done By K Yipon. There Were Approx. 8500cuyds Of Unscreened Contaminated Soil Observed In The Building And Approx. 2500cuyds Of Screened Contaminated Soil Observed In The Building. The Screener Had Broken Down Temporarily And | Soil Was T  
 6/12/2007  Waste Tire Processing Facility Inspection.   Inspection Done By K Yipon. State Inspection For The Waste Tire Permit. The Operators Are Not Burning Any Tires At This Time Since They Are Still Trying To Resolve The Problem Of The Tire Blockages That Occur When The Tires Are Burnt In The Kiln. T  
 8/23/2007  Groundwater Monitoring Report    
 9/7/2007  Groundwater Monitoring Report    
 10/25/2007  Material Recovery/Recycler Inspection.   Inspection Done By K Yipon. The Facility Had Soils Properly Stored Within The Building And The Volumes Were Within The Permitted Limit. The Unacceptable Material Was Also Stored Within The Roofed Area.  
 10/25/2007  Waste Tire Processing Facility Inspection.   Inspection Done By K Yipon. The Facility Operators Were Not Burning Any Tires At The Time Of The Inspection. There Were No Tires Stored Outside But Less Than 100tires Were Stored In A Trailer On Site.  
 2/25/2008  Groundwater Monitoring Report    
 3/7/2008  Soil Treatment Facility Inspection   Inspection Completed By R. Briggle. No Areas Of Concern. Soil Encolsure Contained 7.5tons Of Contaminated Soil. All Soil Was Contained Within The Permitted Structure. Monitoring Wells Were Checked And In Good Condition. Lake Is Being Fill With Muck F  
 9/24/2008  Site Inspection    
 4/23/2009  Site Inspection    
 4/23/2009  Site Inspection    
 10/28/2009  Site Inspection    
 1/5/2010  Site Inspection    
 5/13/2010  Site Inspection    
 11/16/2010  Site Inspection    
 11/16/2010  Site Inspection    
 2/16/2011  Site Inspection    
 5/16/2011  Site Inspection    
 11/16/2011  Site Inspection    
 5/17/2012  Site Inspection    
 12/5/2012  Site Inspection    
 5/13/2013  Site Inspection    
 1/22/2014  Site Inspection    
 4/9/2014  Site Inspection   I Arrived Onsite To Conduct An Inspection. The Site Is Permitted To Use Biomass, Tires, Tire Fluff, And Petroleum Containimated Soil As A Fuel Source. I Was First Taken To The Soil Building Where I Observed 230 Cubic Yards Of Soil. All The Soil Was I  
 2/20/2015  Site Inspection   I Arrived Onsite To Conduct An Inspection. The Site Has A Permit To Use Petroleum Contaminated Soil As A Fuel Source For The Concrete Plant. The Site Has Not Accepted Any Contaminated Soil In Several Months. After Checking In I Was Driven Around The  
 6/9/2015  Site Inspection   I Arrived Onsite To Conduct An Inspection. The Site Has A Permit To Use Tires, Tire Fluff, Biomass, And Contaminated Soil As A Fuel Source. The Site Stopped Using Contaminated Soil Several Months Ago But Continues To Use Tires, Tire Fluff, And Bio M  
 10/8/2015  Site Inspection   I Arrived Onsite To Conduct A Closure Inspection Of The Soil Treatment Facility (Stf) Located Within The Cemex Plant. The Site Inspection Was Conducted In Conjunction With Department Engineer Francisco Teresa-Calleja And Facility Representative Char  
 5/15/2017  Site Inspection   I Arrived Onsite To Conduct An Inspection. The Site Has A Permit To Use Biomass, Waste Tires, And Tire Fluff As A Fuel Source For The Cement Plant. I Was Told By Mr. Walz That The Site Is Currently Only Using Tire Fluff And Plans To Keep It That Way  
 2/26/2018  Site Inspection   I Observed 90 Cubic Yards Of Tire Fluff Onsite. I Was Told By Mr. Hogg That The Facility Has Stopped Accepting Biomass And Has Not Accepted Whole Tires In About A Year.  
 1/17/2019  Site Inspection   I Observed 40 Cubic Yards Of Tire Fluff Onsite. A Small Amount Of Fluff Was Outside The Building.Mr. Hogg Advised Me That One Of The Loaders Was Being Fixed And As Soon As It Was Fixed The Pile Would Be Moved. I Observed Only Permitted Material Onsit  

Violation History

No Violations Found for this EPAID

Vio# Area Regulation Opened
By
Date
Determined