Date Done Activity Type Activity Comments ETA Link
 1/6/2005  Enforcement Project Initiated    
 1/6/2005  Legacy Site Inspection    
 2/11/2005  Warning Letter Issued    
 3/18/2005  Enforcement Meeting    
 4/8/2005  Short Form Consent Order Issued    
 5/11/2005  Draft Consent Order Sent To Ogc  Sep Co  
 6/2/2005  Short Form Consent Order Issued    
 6/23/2005  Short Form Consent Order Executed    
 2/24/2006  Project Closed Letter    
 8/31/2017  Site Inspection  Routine; SQG (100-1000 kg/month)  
 1/24/2018  Federal Significant Noncompliance - Yes  SNY Operating as a TSD without a permit and transporting HW without a manifest; DAY 0: 31-AUG-17  181866
 1/24/2018  Enforcement Tracking    181866
 6/12/2018  Request For Additional Information  Drafted-06/11/2018 - Sent-06/12/2018 - Finished-06/28/2018 - Due Date-07/19/2018  181866
 8/8/2018  Submittal Received By Department  Finished-08/08/2018  181866
 8/22/2018  Meeting  Finished-08/22/2018  181866
 9/20/2018  Submittal Received By Department  Received-09/13/2018 - Finished-09/20/2018  181866
 10/18/2018  Site Inspection  File Review; LQG (>1000 kg/month)  
 8/12/2019  Warning Letter  Forwarded for Review-04/15/2019 - Finished-08/12/2019 - Sent-08/12/2019  181866
 8/30/2019  Submittal Received By Department  Received-08/22/2019 - Finished-08/30/2019  181866
 10/4/2019  Case Report  Drafted-03/08/2018 - Forwarded for Review-03/08/2018 - Sent to OGC-05/01/2018 - Finished-10/04/2019  181866
 11/14/2019  Meeting  Finished-11/14/2019  181866
 2/18/2020  Federal Significant Noncompliance - Yes  SNY FedEx Ground Package System is operating at least 2 unpermitted hazardous waste storage facilities and is transporting hazardous waste without a manifest to facilities not permitted to accept such waste.; DAY 0: 18-OCT-18  187505
 2/18/2020  Enforcement Tracking    187505
 2/26/2020  Case Report  Sent to OGC-05/01/2018 - Finished-02/26/2020  187505
 7/28/2020  Significant Noncompiler Penalty Authorization  Forwarded for Review-04/15/2019 - Approved-08/21/2019 - Approved-07/28/2020 - Finished-07/28/2020  181866
 12/22/2021  Long Form Consent Order  Drafted-07/09/2020 - Sent to OGC-07/09/2020 - Forwarded for Review-11/30/2020 - Issued-12/07/2020 - Executed-12/22/2021  187505

This pulls the Violation History

Violation History

Vio# Area Regulation Opened
By
Date
Determined
Completed ETA Act Act Date Regulation Text Excerpt   (mouse over for more text)
1    262.C  262.34(a)(2)  Kraemer_J  1/6/2005  3/18/2005    10517   1/6/2005   The date upon which each period of accumulation begins is clearly marked and visible for inspection on each container;
2    262.B  262.20  Kraemer_J  1/6/2005  3/18/2005    10517   1/6/2005   General requirements.
3    262.D  262.42  Kraemer_J  1/6/2005  3/18/2005    10517   1/6/2005   Exception reporting.
4    265.B  265.16(a)(1)  Kraemer_J  1/6/2005  3/18/2005    10517   1/6/2005   Facility personnel must successfully complete a program of classroom instruction or on-the-job training that teaches them to perform their duties in a way that ensures the facility's compliance with the requirements of this part. The owner or operato
5    265.C  265.37  Kraemer_J  1/6/2005  3/18/2005    10517   1/6/2005   Arrangements with local authorities.
6      265.50  Kraemer_J  1/6/2005  3/18/2005    10517   1/6/2005   Applicability. The regulations in this subpart apply to owners and operators of all hazardous waste facilities, except as 265.1 provides otherwise.
7    PCR  62-730.240(1), 403.727(1)(b)  White_J  8/31/2017    181866  180947   8/31/2017   No person shall begin operation of a hazardous waste facility without applying for and receiving an operation permit from the Department. Application for operation permits shall be made on DEP Forms 62-730.900(2)(a) through (2)(d) as adopted in parag
8    XXS  62-737.400(5)(a)  White_J  8/31/2017  10/18/2018  181866  180947   8/31/2017   Fragile universal waste devices, universal waste lamps crushed per paragraph (6)(b) below, and lamps or devices showing evidence of leakage, spillage, or damage that could cause leakage, shall be placed in closed containers that are structurally soun
9    XXS  62-737.400(5)(b), 62-737.400(5)(b)1  White_J  8/31/2017  10/18/2018  181866  180947   8/31/2017   Universal waste lamps, devices or the containers in which they are stored shall be labeled or marked clearly as follows:, For universal waste lamps, the words "Spent Mercury-Containing Lamps for Recycling", "Universal Waste Mercury Lamps", "Waste Mer
10    273.B  273.13(d)(1)  White_J  8/31/2017  10/18/2018  181866  180947   8/31/2017   A small quantity handler of universal waste must contain any lamp in containers or packages that are structurally sound, adequate to prevent breakage, and compatible with the contents of the lamps. Such containers and packages must remain closed and
11    262.B, XXS  262.20(a)(1), 403.727(1)(a)  White_J  8/31/2017    181866  180947   8/31/2017   A generator who transports, or offers for transport a hazardous waste for offsite treatment, storage, or disposal, or a treatment, storage, and disposal facility who offers for transport a rejected hazardous waste load, must prepare a Manifest (OMB C
12    XXS  62-730.150(2)(a)  White_J  8/31/2017    181866  180947   8/31/2017   All generators (except generators that are conditionally exempt pursuant to 40 CFR 261.5 [as adopted in subsection 62-730.030(1), F.A.C.]), all transporters, and all persons who own or operate a facility which treats, stores, or disposes of hazardous
13    262.A  262.11  White_J  10/18/2018    187505  187504   10/18/2018   Generators must determine if their solid waste is a hazardous waste
14    264.H  264.140(a)  White_J  10/18/2018    187505  187504   10/18/2018   264.142, 264.143, 264.147-264.151 REQUIREMENTS; EXCEPTIONS
15    264.I  264.175(b)  White_J  10/18/2018    187505  187504   10/18/2018   CONTAINMENT SYSTEM DESIGN AND OPERATION REQUIREMENTS
16    264.E  264.73(a), 264.75, 264.76  White_J  10/18/2018    187505  187504   10/18/2018   WRITTEN OPERATING RECORD AT FACILITY, WHEN TO SUBMIT, WHAT FORM, AND WHAT MUST BE REPORTED:, WHEN AN UNMANIFESTED REPORT IS REQUIRED; FORM WHICH MUST BE USED; INFORMATION IT MUST INCLUDE
17    264.F  264.90(a)(1)  White_J  10/18/2018    187505  187504   10/18/2018   APPLIES TO ALL HW FACILITIES; SATISFY REQUIREMENTS OF 264.90(A)(2)
18    268.A  268.7(a)(1)  White_J  10/18/2018    187505  187504   10/18/2018   Generator of hazardous waste must determine if it has to be treated before it can be land disposed; use standards in 268.40, 268.45, or 268.49; two ways to make determination; explanation & standards.
19    268.A  268.9(a)  White_J  10/18/2018    187505  187504   10/18/2018   Treatment standards under Sub D of Pt 268 by initial generator of a solid waste; code designation & exceptions; if displays hazardous characteristic, must determine defined hazardous constituent.
20    XXS  62-730.150(2)(b)  White_J  10/18/2018    187505  187504   10/18/2018   All generators, transporters, or persons who own or operate a facility which treats, stores, or disposes of hazardous waste, and everyone required to notify under Rule 62-730.181, F.A.C., shall notify the Department of all changes in status and shall
21    264.B  264.15(b)(1), 264.17(b)(4), 264.11, 264.12(b), 264.13(a)(1), 264.13(b), 264.13(c)  White_J  10/18/2018    187505  187504   10/18/2018   DEVELOP AND FOLLOW WRITTEN SCHEDULE, PRECAUTIONS TO PREVENT SPECIFIED REACTIONS, EPA IDENTIFICATION NUMBER REQUIRED, HAZARDOUS WASTE FROM OFF-SITE SOURCE, ANALYSIS REQUIRED PRIOR TO HANDLING ANY HAZARDOUS WASTE OR 264.113(D) NON-HAZARDOUS WASTE; WHAT
22    264.G  264.112(a)(1)  White_J  10/18/2018    187505  187504   10/18/2018   WRITTEN PLAN REQUIRED; CONTINGENT CLOSURE PLANS; SUBMITTED WITH PERMIT; CONDITION OF PERMIT